PAEW, Oman

Project: Rustaq Water Supply Network (2008 – 2010)
Client: PAEW, MOD, POD
Contractor: Hasan Juma Backer T&C LLC
Project detail:
- 1200 KM of pipe laying of various materials and diameters along with Install & Chamber Construction of GV, AV, WO, BV, FMC, FH in Line.
- Construction of Pump Station incl. – guard House, Sub Station, TFS, Yard Piping have Install & Chamber Constr.: PRV, FMC, BV, FCV, AV, WO.
- SCADA system: PLCs, UPS, VFD, HMI, Large TV Screens, FO Cable Networking, Process Instruments & Analyzers and AC Drives etc.